1.0 Purpose
1.1 To describe a procedure for operation and calibration of Muffle Furnace.

2.0 Scope
2.1 This procedure is applicable for operation and calibration of Muffle Furnace located

in Quality Control laboratory at ABC Pvt. Ltd., Roorkee (UK), India.

3.0 Responsibility
Officer QC/ Executive QC Preparation of SOP and follow the procedure as per SOP
Assistant Manager Reviewing and Training of SOP
Manager QC Implementation of SOP

4.0 Accountability
4.1 Manager Quality Control is accountable for implementation and compliance with SOP.

5.0 Procedure
5.1 Operation
5.1.1 Ensure that the Instrument is connected to the power supply.
5.1.2 Switch “ON” the main power supply, glowing of red light at mains indicates the power supply.
5.1.3 Switch on the instrument by ON position which leads to activation of

green control bulb and the temperature controller.
5.1.4 Set the desired temperature (0.0 to 1200) by pressing the ‘Set’ keys provided

at the right bottom front of the Electronic Controller and use ▼▲ keys to increase

or decrease the set value of temperature.
5.1.5 When temperature reaches at the setting point, the green light of temperature

controller automatically switched “OFF” and red light will glow.
5.1.6 The instrument is now ready for operation.
5.1.7 After completion of analysis, pressing the MAINS key OFF the instrument stop.

5.2 Calibration (Frequency: Once a year)
5.2.1 Calibration of temperature controller and temperature mapping of muffle furnace can

be done through external agency from Calibration Service laboratory.
5.2.2 Quality Control-Manager or his designee informs the defect to Maintenance Department

service engineer to rectify the defect. Affix ‘Under Maintenance’ label on the instrument.

5.3 Precaution
5.3.1 Ensure that furnace chamber should be empty when not in use.
5.3.2 Always use longhand tong for placing and removing the crucible in chamber.
5.3.3 Any type of organic solvent should not keep near the instrument.
5.3.4 Before operation of the Muffle Furnace ensures that the input power supply voltage

is 440 V AC. There phase check the display on the volt meter.
5.3.5 If, when connected correctly to the mains, the displays are not lit by pressing

the main switch, check the fuse.
5.3.6 Take suitable precautions to avoid electrical shock by providing proper earthling.
5.4 Cleaning
5.4.1 Do not use any kind of dissolvent and hard brushes.
5.4.2 Use wet cloth and finally wipe with dry cloths to clean the body of the Muffle Furness

6.0 Reference
In house

7.0 Attachments
Not Applicable

8.0 Distribution
Distribution of the controlled copy to concerned departments.
Additional copies may be issued for specific purpose.

9.0 Abbreviations
QA : Quality Assurance
QC : Quality Control
SOP : Standard Operating Procedure
% : Percentage
RPM : Revolution Per Minute

 

10.0 Revision History

Revision No. Supersedes Effective Date Details of Revision
01 Nil New SOP

 

Operating Procedure of Centrifuge

sop for preparation and storage of reagent solution

sop for Calibration and Maintenance of Laboratory Instruments and Equipment

Disposal of Residual Sample or Left Over Material

sop for for Laboratory Incident

standard operating procedure temperature monitoring

sop for drying of silica gel

sop for operation of infrared moisture balance

sop for preparation of mobile phase

sop for treated RO water

sop for Preparation and Issuance of Analysis protocol standard

sop of placebo and impurity stock solutions

sop for disposal of residual sample  

sop for handling of pharmacopoeial changes

sop for procedure for operation of ultrasonic cleaner

difference between UPLC and HPLC

sop for for Emergency Eyewash and Shower

sop for operation and calibration of total organic carbon analyzers

sop for operation of cobb tester

sop for Operation and calibration of atomic absorption spectrophotometer

sop for Operation and calibration of gas liquid chromatograph

sop for operation of humidity oven

sop for operation and calibration of serological water bath

sop for monitoring of drain trap

sop for destruction of analytical samples after testing and control samples

sop for destruction of used chemicals

Sop for Operation of suction pump

sop for Operation and calibration uv cabinet

sop for Operation and calibration of bulk density apparatus

sop for operation and calibration of shore hardness tester

sop for operation of rub proofness tester

sop for monitoring of purified water

sop for Retesting of packaging materials

sop for Retesting and resampling of raw materials

sop for Control of issuance of record of analysis green sheets

sop for Control of computer passwords

sop for sampling of packaging materials PM

Operation and Calibration Procedure for pH Meter

operation and calibration of muffle furnace

Leave a Comment

error: Content is protected !!