analysis of Acarbose 25 mg Tablet
analysis of Acarbose 25 mg Tablet 01. Description : Remove 20 tablets from the strip. Place on a white paper and observe visually. 02. Average Weight: Weigh accurately 20 tablets and calculate … Read more
analysis of Acarbose 25 mg Tablet 01. Description : Remove 20 tablets from the strip. Place on a white paper and observe visually. 02. Average Weight: Weigh accurately 20 tablets and calculate … Read more
Pharma jobs in Roorkee Pharma jobs in Roorkee details are detail given below. 1) computer operators Qualifications B Com Knowledge in tally 2) Store incharge in pharmaceutical Qualifications Graduation 3) Receptionist in pharmaceutical Female Qualification graduation Location Roorkee Contact Heena 8077561364 Mail– rajspice634@gmail.com join our whats app group
sop for Breakdown of Equipment and Machineries 1.0. OBJECTIVE : 1.1 To lay down a procedure for breakdown of equipments and machineries. 2.0. SCOPE : 2.1 This procedure is applicable to attend the breakdown of all Machines, Equipment used in the Plant. 3.0. RESPONSIBILITY : 3.1 HOD of Dept Informed to EM … Read more
Cleaning and Replacement of HVAC LAF Other Clean Air Filters and Monitoring of HEPA Filters OBJECTIVE : 1.1 To lay down a procedure for Procurement, Storage , Cleaning , Replacement of HVAC / LAF / Other clean Air Filters and Monitoring of HEPA Filters. 2.0. SCOPE : 2.1 This procedure is applicable for … Read more
Preventive Maintenance of Building premises and surrounding 1.0 OBJECTIVE : 1.1 To lay down a procedure for carrying out Preventive maintenance of building, premises and surroundings. 2.0. SCOPE : 2.1 This procedure covers painting, civil work to be done in case of wear and tear, maintenance of the door closures, repair of the … Read more
Operation and cleaning of UV bank installed on Purified Water Line 1.0 OBJECTIVE : 1.1 To lay down a procedure for Operation and cleaning of UV bank installed in Purified Water Line. 2.0. SCOPE : 2.1 This procedure is applicable for UV lamps of UV bank installed on Purified Water Line situated … Read more
sop for BMS system handling for Air Handling Unit 1.0 OBJECTIVE : 1.1 To lay down a procedure for carrying out BMS (Building management system system) handling for Air Handling Units 2.0 SCOPE : 2.1 This procedure is applicable to BMS (Building management system system) system for HVAC situated at Pharma dekho. … Read more
sop for Operation of Soft Water Plant 1.0 OBJECTIVE : 1.1 To lay down a procedure for operation of Soft water plant 2.0. SCOPE : 2.1 This procedure is applicable to operation of Soft Water plant 3.0. RESPONSIBILITY : 3.1 Operator Engineering Department shall be responsible for operation of Soft water Plant 3.2 … Read more
sop for Calibration of Dosing Pumps 1.0 OBJECTIVE : 1.1 To lay down a procedure for Calibration of Dosing Pumps. 2.0. SCOPE : 2.1 This procedure is applicable to Calibration of Dosing Pumps Water plant Chemical dosing Pumps at Pharma Dekho . 3.0. RESPONSIBILITY : 3.1 Operator Engineering Department shall be responsible for … Read more
sop for Colour Coding of Pipe line 1.0 OBJECTIVE : 1.1 To lay down a procedure for Colour Coding of Pipe line. 2.0. SCOPE : 2.1 This procedure is applicable for Colour Coding of Pipe line. 3.0. RESPONSIBILITY : 3.1 Operator Engineering Department shall be responsible for Colour Coding of Pipe line. 3.2 … Read more