sop for Operation of Insectocutor
1.0 Objective
To lay down a procedure for operation of Insectocutor.
2.0 Scope
This Standard Operating Procedure is applicable for operation of insectocutor to be followed at
formulation plants of ABC Company
3.0 Responsibility
3.1 Officer/Executive warehouse shall be responsible for operation of Insectocutor.
3.2 Head Warehouse is responsible for implementation of this SOP.
3.3 Head QA or his designee shall be responsible for compliance of this SOP.
4.0 Abbreviations and Definitions
SOP : Standard Operating Procedure
QA : Quality Assurance
WH : Warehouse
5.0 Procedure
5.1 Keep the Insectocutors ‘ON’ for 24 hours.
5.2 Check that both the Fluorescent Tubes of Insectocutors are ‘ON’.
5.3 Ensure that the fluorescent tube is replaced after every 3000 burning hours / 4 months (whichever is earlier or whenever tube is “Out Of Order”).
5.4 Maintain a record therefore in Annexure – 1.
6.0 Forms and Records
6.1 Fluorescent Tube Replacement Record – Annexure -1
7.0 Distribution
7.1 Master Copy – Documentation Cell (Quality Assurance)
7.2 Controlled Copy – Warehouse Department.
8.0 History
| Revision Number | Details For Change | Reason for Revision | 
| 00 | New SOP | NA | 
- process validation protocol for methylcobalamin niacinamide and pyridoxine injection
validation protocol of sterility test sop for Analytical Method Transfer Protocol for hold time study of sterile garments sop for swab sampling for validation of clean surfaces cleaning validation maco and noel calculation formula sop for performance qualification for analyst Sop for Validation report for disinfectant efficacy Sop for Method validation report for bacterial endotoxin test Sop for method validation microbiology sterility testing sop for validation report for preservative efficacy test sop for Protocol cum report for efficacy qualification of uv light sop for validation protocol for uv light efficacy of dpb & laf sop for cleaning validation protocol tablet manufacturing equipment 
 
 
 
 sop for cleaning validation protocol ointment manufacturing equipmentconcurrent process validation for rabeprazole ec and domperidone sr capsules sop for Validation for cleaning procedure liquid injection sop for Validation for cleaning procedure dry powder injection Preparation Approval Control and Distribution of Master Formula Records calibration policy for equipment and instruments evaluation Sampling of Raw Materials questionnaire training evaluation questionnaire sop for approval of Contract Parties sop for Operation and Cleaning of Purified Water Generation System sop for Storage of Standard Weights sop for Dispensing of Raw Material Receipt of Excess RM/PM from Production sop for Dispatches of Finished Goods Cleaning of Dispensing and Sampling Area procedure for cleaning of dispensing tools Cleaning and Operation of Reverse Laminar Air Flow Handling of Open-Damaged Containers in Warehouse sop for Discard of Scrap From Warehouse Cleaning and Operation of Reverse Laminar Air Flow sop for Cleaning of High Racks sop for Issuance of Excess RM/PM to Production sop for Cleaning of MS Shutter procedure for handling of rejected materials sop for Generation of Goods Receipt Note 