sop for Operation of Insectocutor

 

sop for Operation of Insectocutor

 

1.0 Objective
To lay down a procedure for operation of Insectocutor.
2.0 Scope
This Standard Operating Procedure is applicable for operation of insectocutor to be followed at

formulation plants of ABC Company
3.0 Responsibility
3.1 Officer/Executive warehouse shall be responsible for operation of Insectocutor.
3.2 Head Warehouse is responsible for implementation of this SOP.
3.3 Head QA or his designee shall be responsible for compliance of this SOP.
4.0 Abbreviations and Definitions
SOP : Standard Operating Procedure
QA : Quality Assurance
WH : Warehouse
5.0 Procedure
5.1 Keep the Insectocutors ‘ON’ for 24 hours.
5.2 Check that both the Fluorescent Tubes of Insectocutors are ‘ON’.
5.3 Ensure that the fluorescent tube is replaced after every 3000 burning hours / 4 months (whichever is earlier or whenever tube is “Out Of Order”).
5.4 Maintain a record therefore in Annexure – 1.
6.0 Forms and Records
6.1 Fluorescent Tube Replacement Record – Annexure -1

7.0 Distribution
7.1 Master Copy – Documentation Cell (Quality Assurance)
7.2 Controlled Copy – Warehouse Department.
8.0 History

Revision Number Details For Change
Reason for Revision
00 New SOP NA
process validation protocol for methylcobalamin niacinamide and pyridoxine injection

validation protocol of sterility test

sop for Analytical Method Transfer

Protocol for hold time study of sterile garments

sop for process validation

sop for swab sampling for validation of clean surfaces

cleaning validation maco and noel calculation formula

sop for performance qualification for analyst

Sop for Validation report for disinfectant efficacy

Sop for Method validation report for bacterial endotoxin test

Sop for method validation microbiology sterility testing

sop for validation report for preservative efficacy test

sop for Protocol cum report for efficacy qualification of uv light

sop for validation protocol for uv light efficacy of dpb & laf

sop for cleaning validation protocol tablet manufacturing equipment



sop for cleaning validation protocol ointment manufacturing equipment

concurrent process validation for rabeprazole ec and domperidone sr capsules

sop for Validation for cleaning procedure liquid injection

sop for Validation for cleaning procedure dry powder injection

sop for validation plan

Preparation Approval Control and Distribution of Master Formula Records

calibration policy for equipment and instruments

sop for stability management

evaluation Sampling of Raw Materials questionnaire

training evaluation questionnaire

sop for approval of Contract Parties

sop for Operation and Cleaning of Purified Water Generation System

sop for Storage of Standard Weights

sop for Dispensing of Raw Material

Receipt of Excess RM/PM from Production

sop for Dispatches of Finished Goods

Cleaning of Dispensing and Sampling Area

procedure for cleaning of dispensing tools

Cleaning and Operation of Reverse Laminar Air Flow

Handling of Open-Damaged Containers in Warehouse

sop for Discard of Scrap From Warehouse

Cleaning and Operation of Reverse Laminar Air Flow

sop for Cleaning of High Racks

sop for Issuance of Excess RM/PM to Production

sop for Cleaning of MS Shutter

procedure for handling of rejected materials

sop for Generation of Goods Receipt Note

sop for handling of re-test materials

sop for Spillage Control

sop for Operation of Insectocutor

 

Leave a Comment

error: Content is protected !!