1.0 Objective
To lay down a procedure for verification of weighing balances in warehouse.
2.0 Scope
This Standard Operating Procedure is applicable for verification of weighing balances in warehouse to be followed at

formulation plants of A B C  Pvt. Ltd.
3.0 Responsibility
3.1 Officer  Executive warehouse shall be responsible for the verification of weighing balances.
3.2 Head Warehouse is responsible for ensuring the verification of weighing balances.
3.3 Head QA or his designee shall be responsible for implementation and compliance with SOP.
4.0 Abbreviations and Definitions
SOP : Standard Operating Procedure
i.e. : That is
No : Number
w.r.t : With respect to
WH : Warehouse
HOD : Head of Department
5.0 Procedure
5.1 Ensure the cleanliness of the weighing balance.
5.2 Ensure that the balances, which are kept under R-LAF, shall be calibrated and operated while R-LAF unit is switched ‘ON’.
5.3 Check the spirit level of the balance, if required adjusts from the base screw. Record it in the format as applicable as

per the balance capacity.
5.4 Switch “ON” the main electric supply of the balance.
5.5 Press the “ON” button of the instrument.
5.6 Allow the balance display to come in stable state.
5.7 Press “Zero” button and ensure zero reading on the display board of the balance.
5.8 Select two standard weights of higher & lower limit given.
5.9 Place the standard weights one by one on the weighing platform / pans and check the readings.

Recording shall be done in the relevant format.
5.10 A balance is considered satisfactory for use if the readings are found to be within acceptance limit of the balance as

mentioned in the respective annexure for a balance.
5.11 If the reading is out of acceptance limit, put an “UNDER MAINTENANCE” label and inform the head of the

department and engineering department for necessary action.
5.12 After rectification, calibrate the balance before use and enter the same in the ‘Balance verification record’.
5.13 Use the standard weights duly certified by the weights and measures department.
6.0 Forms and Records
6.1 None
7.0 Distribution
7.1 Master Copy – Documentation Cell (Quality Assurance)

7.2 Controlled Copy – Warehouse Department.

sop for operation and cleaning of Hand coder

sop for Cleaning and Handling and Silicone Tubes

sop on operation and cleaning of coating pan

sop for Operation of cleaning of pipe lines

Sop for equipment assembly

sop for operation of capsule loading machine semi automatic

sop for Machine operation capsule inspection and polishing machine

Sop for issue of material

Sop batch demarcation and batch coding

sop for material receipts

sop for monitoring of reprocessing of products

sop for in-process control on liquids orals

sop for in process controls on tablets capsules packaging line

sop for Issuance retrieval and destruction of BMR and analytical records

sop for in process controls during granulation compression coating inspection

sop for Cleaning of Blister packing machine

sop for cleaning of dust exhausts

Entry Exit and Gowning Procedure in Dispensing Area

sop for Receipt and Storage of Raw Materials

sop for Verification of Weighing Balances

Leave a Comment

error: Content is protected !!