1.0 OBJECTIVE :

1.1 To lay down a procedure for chlorination of raw water.

2.0. SCOPE :

2.1 This procedure is applicable to raw water store in underground raw water storage tank situated at Pharma Dekho

3.0. RESPONSIBILITY :

3.1 Operator Engineering Department shall be responsible for preparation of chlorine solution and checking chlorine dosage and record the same in log book.
3.2 Officer/Executive Engineering Department shall be responsible for assurance of proper dosing and to take corrective action if any deviation.
4.0. ACCOUNTABILITY :
4.1 Head Engineering Department shall be accountable for compliance of SOP.
5.0. PROCEDURE :
5.1 SOLUTION PREPARATION:
5.1.1 Prepare the solution on daily basis.
5.1.2 Take 10 liters 4 % sodium hypochlorite solution in chemical dosing tank and add 10-liter potable water.
5.1.3 Mix the solution with cleaned SS stirrer.
5.1.4 Sodium hypo chlorite tank is connected with inlet tube of dosing pump is connect with sensor as this sensor installed in raw water pipe line.

5.4 METHOD FOR DETERMINATION OF RESIDUAL FREE CHLORINE BY CHLORINE TEST KIT.
5.4.1 Take 25 ml. of chlorinated water into the test jar.
5.4.2 Add half a micro-spoon (80-90 mg) of Reagent – A.
5.4.3 If pink color appears free chlorine is present in the sample. If not appear free chlorine is absent in the sample.
5.4.4 Adds Reagent –B drop by drop till the pink colour is discharged. Shake the jar after the addition of each drop.
5.4.5 Count the number of drops while adding. Each drop of Reagent B = 0.1 ppm of chlorine.



6.0. ABBREVIATION :

Sr. No. Abbreviation used Full form of abbreviation used
1. SOP Standard operating procedure
2. EM Engineering and maintenance
3. PPM Parts per Million

 

ATTACHMENTS (ANNEXES) :
7.1 Annex-I : Sodium hypo chloride dosing record
7.2 Annex- II : Sodium hypo chloride consumption record
7.3 Annex III : Chlorine content neutralization record
8.0. REFERENCE :

In House


Annex-I : Sodium hypo chloride dosing record

  Annex- II : Sodium hypo chloride consumption record

Annex III : Chlorine content neutralization record

sop for Operation and regeneration of softener plant

Procedure Of Issuance Of material from Engineering Store

sop for Preventive Maintenance of Filter Press

sop for Preventive Maintenance of Sugar Transfer System

sop for Preventive Maintenance of Shrink Sleeve Machine

sop for Preventive Maintenance of ROPP Cap Elevator

sop for Preventive Maintenance of Liquid Transfer Pumps

sop for Preventive Maintenance of Liquid Tanks

Preventive Maintenance of Strip De-Foiling Machine

sop for Preventive Maintenance of Colloidal Mill

sop for Preventive Maintenance of Packing Collator Belt

sop for Checking light intensity

sop for Operation of Fire- Extinguisher

sop for Passivation of WFI Distribution Loop

sop for Analysis of Effluent Treatment Plant Water

sop for Methodology to Dispose ETP Sludge

sop for Action Plan In Case Of Electrical Power Failure

sop for Colour Coding of Piping and Accessories of Utilities

sop for Replacement Policy

sop for Disposal of Engineering Waste

Filter Cleaning of HVAC System RLAF & LAF

Procedure for Calibration of Magnehelic Gauge

Procedure for Calibration of Vacuum Gauge

Procedure for Calibration of Pressure Gauge

sop for Procedure for Calibration of Temperature Controller

sop for Area Validation

sop for Preventive Maintenance of Infrared Dryer Umbrella Type

sop for Preventive Maintenance of Battery stacker

sop for Preventive Maintenance of Lift

sop for Preventive Maintenance of Vacuum Cleaner

sop for Preventive Maintenance of laminar air flow unit

sop for Preventive Maintenance of Lozenges Manufacturing Line

sop for Preventive Maintenance of Garment Washing Machine

sop for Preventive Maintenance of Multi Column Distillation Plant

sop for Preventive Maintenance of Steam Sterilizer Autoclave

sop for Preventive Maintenance of Pure steam Generator

sop for Preventive maintenance of Depyrogenating Tunnel

sop for Preventive Maintenance of vial sealing machine

sop for preventive maintenance of Powder Filling and Rubber Stoppering machine

sop for Preventive Maintenance of Vial Washing Machine

sop for Preventive Maintenance of Inspection Table

sop for Preventive Maintenance of Hi-Cart

sop for Preventive Maintenance of Turn table

sop for Preventive Maintenance of sticker labeling machine

sop for Preventive Maintenance of Liquid Filling and Sealing Machine

sop for Preventive Maintenance of Linear Bottle Washing Machine

sop for Preventive Maintenance of De-Foiling Machine

sop for Preventive Maintenance of Strip Packing Machine

sop for Preventive Maintenance of Blister Packing Machine

sop for Preventive Maintenance of Capsule Polishing and Sorting Machine

sop for Preventive Maintenance of Capsule Filling Machine 

sop for Preventive maintenance of Auto Coater

sop for Preventive Maintenance of Compression Machine

sop for preventive maintenance of packing conveyor belt

sop for Preventive Maintenance of Sifter Cum Multi mill

sop for Preventive Maintenance of Rapid Mixer Granulator

sop for Preventive Maintenance Of Fluid Bed Dryer

sop for Preventive Maintenance of Octagonal Blender

sop for Preventive Maintenance of Lifting and Positioning Device

sop for Preventive Maintenance of Paste Preparation vessel

sop for preventive maintenance of Vibro-Sifter

sop for preventive maintenance of air curtain

sop for preventive maintenance of air handling units

Preventive Maintenance of Diesel Generator

sop for Preventive Maintenance of cooling towers

sop for Preventive Maintenance of Boiler

sop for Preventive Maintenance of Air Compressor

sop for Preventive Maintenance of Chilling Plant

sop for Preventive Maintenance of Transformers

sop for Preventive maintenance of Purified Water System

sop for Break Down maintenance of Machine and Work Requisition

sop for Building Maintenance

sop for Operation of Air Compressor and Air Dryer

procedure for chlorination of raw water

Exit mobile version