1.0 OBJECTIVE :

1.1 To lay down a procedure for Replacement of Brine Solution of Homogenizer Chiller.

2.0. SCOPE :

2.1 This procedure is applicable to replacement of brine solution of homogenizer chiller situated at pharma Dekho

3.0. RESPONSIBILITY :

3.1 Operator shall be responsible for the replacement of brine solution of homogenizer chiller.
3.2 Officer/Executive Engineering Department shall be responsible for to verify the replacement of brine solution of homogenizer chiller.
3.3 Quality control personal will be responsible for analysis of Specific gravity.

4.0. ACCOUNTABILITY :



4.1 Head Engineering Department shall be accountable for compliance of SOP.

5.0. PROCEDURE :
.
5.1 PRIMARY CHECKS:
5.1.1. Ensure that the availability of Glycerol 25 Liter.
5.1.2. Ensure that the Circulation pump & Chiller is switched ‘Off’.
5.1.3. Display the ‘Under Maintenance Board’.

5.2. PROCEDURE:
5.2.1 Open the top cover of Homogenizer Chiller tank.
5.2.2 Take out the Brine Solution from tank.
5.2.3 Properly clean the tank inside with purified water.
5.2.4 After cleaning of tank, load the new solution of brine of 75 Liter purified water and 25 Liter Glycerol in 100Ltrs of Tank.
5.2.5 Take 5 ml sample of new solution of brine and check the specific gravity by authorized person of QC and Log in the Annex-II.
5.2.6 Specific gravity of new solution of brine shall be more than 1.04 then close the top cover.
5.2.7 After closing the tank of Homogenizer Chiller, run the Homogenizer Chiller for 2 hours and takes the reading of temperature at every 15 min. & fill the Temp. record as per Annex-III.
5.2.8 If the Homogenizer Chiller achieves the Set Temperature successfully at 15 min reading & continued for the rest of time.
5.2.9 Frequency of replacement of brine solution of homogenizer chiller : Quarterly
5.2.10 Fill the replacement record of brine solution as per Annex-I.



6.0. ABBREVIATION :

Sr. No. Abbreviation used Full form of abbreviation used
1 SOP Standard operating procedure
2 EM Engineering and maintenance

7.0 ATTACHMENTS (ANNEXES) :
7.1 Annex-I: Homogenizer Chiller Brine (Glycerol + Water) Replacement Record.
7.2 Annex-II: Specific Gravity of 5 ml Brine Solution.
7.3 Annex-III: Homogenizer Chiller Temp Monitoring Log.

8.0. REFERENCE :

In House

 

Annex-I: Homogenizer Chiller Brine (Glycerol + Water) Replacement Record

Annex-II: Specific Gravity of 5 ml Brine Solution.

Annex-III: Homogenizer Chiller Temp Monitoring Log.

Online Rejection in parenteral

Receipt of Batch from Production to Packing Department

sop for for Spillage Handling in parenteral area

sop for calibration of vessels with dipstick

sop for Cleaning of Bins and Containers

cip of mixing vessel and holding vessel

SOP FOR BATCH MANUFACTURING

sop for placebo batch

sop for Cleaning of Ampoule Filling and Sealing Machine

sop for Fogging in Sterile and Non Sterile Area

sop for for Filtration of Bulk Solution

sop for fumigation in production area

sop for post cleaning after media fill

sop for cip of mixing vessel mixing mobile vessel and holding vessel

sop for De-Bagging of Three Piece Vial Dropper Caps

sop for calibration and verification of check weigher

sop for Batch number and Manufacturing and Expiry Date Coding System

sop for Sanitization of Seals

standard operating procedure machine history file

sop for operation and cleaning of Hand coder

sop for Cleaning and Handling and Silicone Tubes

sop on operation and cleaning of coating pan

sop for Operation of cleaning of pipe lines

Sop for equipment assembly

sop for operation of capsule loading machine semi automatic

sop for Machine operation capsule inspection and polishing machine

Sop for issue of material

Sop batch demarcation and batch coding

sop for material receipts

sop for monitoring of reprocessing of products

sop for in-process control on liquids orals

sop for in process controls on tablets capsules packaging line

sop for Issuance retrieval and destruction of BMR and analytical records

sop for in process controls during granulation compression coating inspection

sop for Cleaning of Blister packing machine

sop for for charge hand over between the shifts

Performance requalification report of visual inspectors

sop for Cleaning and operation of ROPP caps inspection table

sop for usage and destruction of filter pad and cartridge filter

sop for cleaning and storage of transfer pipe

sop for Cleaning and operation of labeling machine

Cleaning and operation of the mono block filling and sealing machine

sop for Cleaning and operation of empty bottle inspection table

sop for Cleaning and operation of filter press

sop for cleaning and operation of liquid transfer pump and line

sop for cleaning and operation of storage vessels




sop for cleaning and operation of sugar syrup manufacturing vessel

sop for cleaning issuance and retrieval of accessories and change parts

sop for Cleaning and operation of visual inspection conveyor belt

sop for Cleaning and operation of spray gun and assemble

sop for Cleaning of Air Handling Unit Ducting

sop for Uninterrupted Power Supply UPS

sop for Operation of Chiller and Pumps

sop for Preventive Maintenance of Equipments and Machineries

sop for cleaning of Dosing tank

Replacement of Activated Charcoal and Cartridges Oil Filter of N2 Plant

procedure for Replacement of Brine Solution of Homogenizer Chiller

 

Leave a Comment

error: Content is protected !!