1.0 OBJECTIVE :

1.1 To lay down a procedure for Replacement of Activated Charcoal and Cartridge oil filter of N2 Plant.

2.0. SCOPE :

2.1 This procedure is applicable for replacement of Activated Charcoal and Cartridge Oil filter of N2 Plant situated at Pharma Dekho.

3.0. RESPONSIBILITY :

3.1 Operator Engineering Department shall be responsible for replacement of Activated Charcoal and Cartridge Oil filter and maintain the record.
3.2 Officer/Executive Engineering Department shall be responsible for to verify the replacement of Activated Charcoal and Cartridge oil filter and to take corrective action if any operational deviation.



4.0. ACCOUNTABILITY :

4.1 Head Engineering Department shall be accountable for compliance of SOP.

5.0. PROCEDURE :

5.1 PRIMARY CHECKS:
5.1.1. Ensure that the availability of new Activated Charcoal & cartridge oil filter.
5.1.2. Ensure that the Nitrogen plant should be switched ‘Off’.
5.1.3. Display the ‘Under Maintenance Board’ on N2 Plant.

5.2. PROCEDURE FOR REPLACMENT OF ACTIVATED CHARCOAL:

5.2.1 Open the Activated Charcoal filter vessel top cover & drain cover.
5.2.2 Take out the old Activated Charcoal from the vessel into the poly bag & keep it to designated place.
5.2.3 Clean the vessel from inside with fresh water properly. After cleaning of vessel, close the drain cover.
5.2.4 Take the new Activated Charcoal in a plastic container and clean it to with fresh water.
5.2.5 Load the cleaned Activated Charcoal in to the vessel.
5.2.6 Fit the vessel top cover & remove the under maintenance status board.
5.2.7 Start the N2 plant as per the current version of . SOP No.
5.2.8 Frequency of replacement of Activated charcoal once in eighteen months.
5.2.9 Fill the replacement record of Activated Charcoal in Annex –I.



5.3. PROCEDURE FOR REPLACMENT OF CARTRIDGE OIL FILTER:

5.3.1 Frequency for replacement of cartridge oil filter as mentioned below

Sr. No. Area / System Filter ID No. Filter Rating

(in micron)

Frequency for replacement
1    Nitrogen Plant NF-01 0.1µ 08 month
2 Nitrogen Plant NF-02 0.01µ 08 month
3 Nitrogen Plant NF-03 0.01µ 08 month
4 Nitrogen Line NF-04 0.1µ 08 month
5 Nitrogen Line NF-05 0.01µ 08 month

5.3.2 Fill the record of replacement of Cartridge Filter replacement in Annex-II

 

6.0. ABBREVIATION :

Sr. No. Abbreviation used Full form of abbreviation used
1. SOP Standard operating procedure
2. EM Engineering and maintenance
3 N2 Nitrogen

7.0 ATTACHMENTS (ANNEXES) :

Annex-I: Replacement record of Activated Charcoal.

Annex-II: Replacement record of cartridges oil filter.

8.0. REFERENCE :

In House

 

Annex-I: Replacement record of Activated Charcoal.

 

Annex-II: Replacement record of cartridges oil filter.

Online Rejection in parenteral

Receipt of Batch from Production to Packing Department

sop for for Spillage Handling in parenteral area

sop for calibration of vessels with dipstick

sop for Cleaning of Bins and Containers

cip of mixing vessel and holding vessel

SOP FOR BATCH MANUFACTURING

sop for placebo batch

sop for Cleaning of Ampoule Filling and Sealing Machine

sop for Fogging in Sterile and Non Sterile Area

sop for for Filtration of Bulk Solution

sop for fumigation in production area

sop for post cleaning after media fill

sop for cip of mixing vessel mixing mobile vessel and holding vessel

sop for De-Bagging of Three Piece Vial Dropper Caps

sop for calibration and verification of check weigher

sop for Batch number and Manufacturing and Expiry Date Coding System

sop for Sanitization of Seals

standard operating procedure machine history file

sop for operation and cleaning of Hand coder

sop for Cleaning and Handling and Silicone Tubes

sop on operation and cleaning of coating pan

sop for Operation of cleaning of pipe lines

Sop for equipment assembly

sop for operation of capsule loading machine semi automatic

sop for Machine operation capsule inspection and polishing machine

Sop for issue of material

Sop batch demarcation and batch coding

sop for material receipts

sop for monitoring of reprocessing of products

sop for in-process control on liquids orals

sop for in process controls on tablets capsules packaging line

sop for Issuance retrieval and destruction of BMR and analytical records

sop for in process controls during granulation compression coating inspection

sop for Cleaning of Blister packing machine

sop for for charge hand over between the shifts

Performance requalification report of visual inspectors

sop for Cleaning and operation of ROPP caps inspection table

sop for usage and destruction of filter pad and cartridge filter

sop for cleaning and storage of transfer pipe

sop for Cleaning and operation of labeling machine

Cleaning and operation of the mono block filling and sealing machine

sop for Cleaning and operation of empty bottle inspection table

sop for Cleaning and operation of filter press

sop for cleaning and operation of liquid transfer pump and line

sop for cleaning and operation of storage vessels




sop for cleaning and operation of sugar syrup manufacturing vessel

sop for cleaning issuance and retrieval of accessories and change parts

sop for Cleaning and operation of visual inspection conveyor belt

sop for Cleaning and operation of spray gun and assemble

sop for Cleaning of Air Handling Unit Ducting

sop for Uninterrupted Power Supply UPS

sop for Operation of Chiller and Pumps

sop for Preventive Maintenance of Equipments and Machineries

sop for cleaning of Dosing tank

Replacement of Activated Charcoal and Cartridges Oil Filter of N2 Plant

 

 

Leave a Comment

error: Content is protected !!