sop for Audio Visual Alarms of various systems
1.0 OBJECTIVE :
1.1 To lay down a procedure for rectification of audio visual alarms of various systems..
2.0. SCOPE :
2.1 This procedure is applicable to Stability chamber, BOD Incubator, N2, O2 and Granulation/Coating AHU’S situated at Pharma Dekho.
3.0. RESPONSIBILITY :
3.1 Engineering and Maintenance Department.
4.0. ACCOUNTABILITY :
4.1 Head of Engineering Department shall be responsible for compliance of SOP.
5.0. PROCEDURE :
5.1 Audio visual Alarming system for Stability chambers and BOD Incubators
5.1.1 This Audio Visual Alarming system installed for stability chamber BOD Incubator and Hooters at utility Alarm panel board.
5.1.2 Description of audio visual alarms
Sr. No | Equipment ID | Equipment Name | TEMP (ºC) | RH % | ||
Set | Limit | set | Limit | |||
1. | STABILITY CHAMBER-1 | 30 | 28 – 32 | 75 | 70 – 80 | |
2. | STABILITY CHAMBER-2 | 40 | 38 – 42 | 75 | 70 – 80 |
5.1.3 This Audio Visual Alarming system functions when out of limit values observed for temperature/RH (as per 5.1.2) in stability chamber/BOD Incubators.
5.1.4 Add out of limit of Temp./RH in Stability chamber/BOD Incubator, the alarm system gives audio/visual alarms on Panel.
5.1.5 Immediate Operator checks, the signal of Particular stability/BOD Incubator in panel.
5.1.6 Operator acknowledge the alarms of particular system and immediately attend the system.
5.1.7 The Operator shall verify the failures of Stability chamber/BOD Incubator as per below mention check points.
( i) Failure of power supply.
(ii) Failure of Cooling compressor/Fan.
(iii) Failure of heater.
(iv) Failure of steam bath in stability chamber.
(v) Controller for Temp. and RH.
5.1.8 After rectification of failure cause, observe particular system for one hour for proper functioning.
5.1.9 Re-set the alarm switch in alarm panel board after rectification and
fill up annex-I.
5.1.10 Inform to concern dept Head for rectification.
5.2 Audio visual Alarming system for N2 and O2 cylinders
5.2.1 The Audio Visual Alarming system installed for N2 and O2 supply station and Hooter at utility alarm panel board.
5.2.2 When N2 and O2 pressure goes below to 3.5 kg/cm², than the alarm shall be generated .
5.2.3 Replaced empty cylinder with filled cylinder.
5.3 Audio visual Alarming system for Temp. of Coating and Granulation AHU’S
5.3.1 The Audio Visual Alarming system installed for hot water storage tank for Coating and Granulation AHU’S at utility.
5.3.2 Audio visual alarming panel installed at utility alarm panel board.
5.3.3 When the temp. of hot water goes below to 60ºC then alarm shall be generated.
5.3.4 Check the heater of hot water, verify it and record.
5.3.5 If temperature not achieved within 10 minutes operator shall inform the engg. And concern dept. head.
6.0. ABBREVIATION :
Sr. No. | Abbreviation used | Full form of abbreviation used |
1. | SOP | Standard operating procedure |
2. | EM | Engineering and maintenance |
7.0 ATTACHMENTS (ANNEXES) :
Annex-I : LOG SHEET FOR STABILITY AND BOD INCUBATOR ALARM SYSTEM
Annex-II : LOG SHEET FOR N2/O2 ALARM SYSTEM
8.0. REFERENCE :
Annex-I : LOG SHEET FOR STABILITY AND BOD INCUBATOR ALARM SYSTEM
Annex-II : LOG SHEET FOR N2/O2 ALARM SYSTEM
Online Rejection in parenteral
Receipt of Batch from Production to Packing Department
sop for for Spillage Handling in parenteral area
sop for calibration of vessels with dipstick
sop for Cleaning of Bins and Containers
cip of mixing vessel and holding vessel
sop for Cleaning of Ampoule Filling and Sealing Machine
sop for Fogging in Sterile and Non Sterile Area
sop for for Filtration of Bulk Solution
sop for fumigation in production area
sop for post cleaning after media fill
sop for cip of mixing vessel mixing mobile vessel and holding vessel
sop for De-Bagging of Three Piece Vial Dropper Caps
sop for calibration and verification of check weigher
sop for Batch number and Manufacturing and Expiry Date Coding System
standard operating procedure machine history file
sop for operation and cleaning of Hand coder
sop for Cleaning and Handling and Silicone Tubes
sop on operation and cleaning of coating pan
sop for Operation of cleaning of pipe lines
sop for operation of capsule loading machine semi automatic
sop for Machine operation capsule inspection and polishing machine
Sop batch demarcation and batch coding
sop for monitoring of reprocessing of products
sop for in-process control on liquids orals
sop for in process controls on tablets capsules packaging line
sop for Issuance retrieval and destruction of BMR and analytical records
sop for in process controls during granulation compression coating inspection
sop for Cleaning of Blister packing machine
sop for for charge hand over between the shifts
Performance requalification report of visual inspectors
sop for Cleaning and operation of ROPP caps inspection table
sop for usage and destruction of filter pad and cartridge filter
sop for cleaning and storage of transfer pipe
sop for Cleaning and operation of labeling machine
Cleaning and operation of the mono block filling and sealing machine
sop for Cleaning and operation of empty bottle inspection table
sop for Cleaning and operation of filter press
sop for cleaning and operation of liquid transfer pump and line
sop for cleaning and operation of storage vessels
sop for cleaning and operation of sugar syrup manufacturing vessel
sop for cleaning issuance and retrieval of accessories and change parts
sop for Cleaning and operation of visual inspection conveyor belt
sop for Cleaning and operation of spray gun and assemble
sop for Cleaning of Air Handling Unit Ducting
sop for Uninterrupted Power Supply UPS
sop for Operation of Chiller and Pumps
sop for Preventive Maintenance of Equipments and Machineries
sop for cleaning of Dosing tank
sop for Audio Visual Alarms of various systems