sop for Preventive Maintenance of Rapid Mixer Granulator
1.0 Objective
To lay down a procedure for the Preventive Maintenance of Rapid Mixer Granulator.
2.0 Scope
This Standard Operating Procedure is applicable for Preventive Maintenance of Rapid Mixer Granulators to be followed at formulation plants
3.0 Responsibility
3.1 Engineering Officer / Executive shall be responsible for the execution of this procedure.
3.2 Engineering Manager shall be responsible for the implementation of this SOP.
3.3 Head QA/designee should be responsible for compliance of this SOP.
4.0 Abbreviations and Definitions
SOP : Standard Operating Procedure
No : Number
QA : Quality assurance
Qty : Quantity
RMG : Rapid Mixer Granulator
5.0 Procedure
5.1 General Conditions
5.1.1 Refer the master plan of preventive maintenance.
5.1.2 Equipment shall be available for preventive maintenance.
5.1.3 Clean oil / grease stains & remove unwanted material, spares after completion of work.
5.2 Precautions
5.2.1 Use necessary safety wears, while doing the work.
5.2.2 Ensure covers & guards are properly fixed.
5.3 Procedure for Preventive Maintenance of Rapid Mixer Granulator
5.3.1 Ensure that electrical supply is in off position in main panel and display “Under Maintenance” Board on the panel board.
5.3.2 Switch OFF the drive unit and inform all the concerned.
5.3.3 Operator or above has to ensure and verify the check points for the preventive maintenance as shown in the annex – 1, 2&3.
5.3.4 After the completion of preventive maintenance, check the machine for smooth operation.
5.3.5 Remove “Machine under Maintenance” Board on the panel board after completion of the Maintenance.
5.3.6 The operator / technician who perform the job will enter his name / sign in “Done By” Column and responsible Engineer/ Officer and Officer – Production will put sign in “Checked by” column.
5.3.7 Half Yearly Maintenance will include the jobs of Monthly and Quarterly Maintenance and Yearly maintenance will include the jobs of Monthly, Quarterly and half yearly maintenances.
5.3.8 Quarterly Preventive Maintenance is to be carried out as per the following check points.
5.3.8.1 Check the spider of motor and gearbox coupling.
5.3.8.2 Check and tighten all nuts and bolts of the m/c.
5.3.8.3 Check the oil level in gear box, if required top up the oil with 320 grade lubricating oil.
5.3.8.4 Check the foundation bolts of chopper motor.
5.3.8.5 Check the all gasket for any damage, if required replace.
5.3.8.6 Check all the locking bolts; if required replace.
5.3.8.7 Check the chopper blade lock bolt; if required tight.
5.3.8.8 Check the impeller / blade lock nuts; tighten the same.
5.3.8.9 Check the all electrical terminal connections and tighten the same.
5.3.8.10 Check the seal of impeller; for any leakage, if required replace the same.
5.3.8.11 Check the bearing of chopper motor; if required lubricate with grease.
5.3.8.12 Check the air purging pipes for any choking / damage if required clean or replace it.
5.3.8.13 Check all safety operations, if found any abnormality rectify the problem.
5.3.8.14 Check the proper earthing.
5.3.9 Half Yearly Preventive Maintenance is to be carried out as per the following check points.
5.3.9.1 Check all electrical points of main panel board for any loose connections & tighten up accordingly.
5.3.9.2 Check the all-motor terminal connections and tighten the same.
5.3.10 Yearly Preventive Maintenance is to be carried out as per the following check points.
5.3.10.1 Check the chopper motor bearings for wear tear & replace.
5.3.10.2 Check the main gearbox bearings for wear tear & replace accordingly.
5.3.10.3 Check the oil seal of gearbox for wear tear & replace accordingly.
5.3.10.4 Check all electrical connections (compressor control panel, all pump motors, fan motor) for any loose connections, burned contacts, signs of overheated wires etc.
6.0 Forms and Records
6.1 Quarterly Preventive Maintenance Check List of RMG
6.2 Half Yearly Preventive Maintenance Check List of RMG
6.3 Yearly Preventive Maintenance Check List of RMG
7.0 Distribution
7.1 Master copy – Documentation Cell (Quality Assurance)
7.2 Controlled copies – Engineering Department
sop for Execution of Preventive Maintenance
Preparation of Sodium Hydroxide Solution
sop for water cooled chiller operation
cleaning and preventive maintenance of LAF and RLAF
sop for replacement of water system filters
cleaning and preventive maintenance of insectocutor
sop for operation of preventive maintenance
sop for material receiving and consumption record
sop for Preventive maintenance of bottle washing machine
sop for Replacement of Battery of Electronic Devices
sop for Preparation of R.O. Antiscalant Solution
Preventive Maintenance of Rapid Cooling Steam Sterilizer
Preventive Maintenance of Rapid cooling steam Generator
sop for Preventive Maintenance of Dust Collector
sop for Replacement of HVAC filters
SOP for Battery Backup in Mobile Laminar Air Flow Trolley
sop for Replacement of Tube lights
sop for Replacement of UV light of purified water plant
sop for Cleaning of soft water storage tank and RO feed tank
sop for Preparation of Sodium hydroxide Solution
sop for Operation and regeneration of softener plant
Procedure Of Issuance Of material from Engineering Store
sop for Preventive Maintenance of Filter Press
sop for Preventive Maintenance of Sugar Transfer System
sop for Preventive Maintenance of Shrink Sleeve Machine
sop for Preventive Maintenance of ROPP Cap Elevator
sop for Preventive Maintenance of Liquid Transfer Pumps
sop for Preventive Maintenance of Liquid Tanks
Preventive Maintenance of Strip De-Foiling Machine
sop for Preventive Maintenance of Colloidal Mill
sop for Preventive Maintenance of Packing Collator Belt
sop for Checking light intensity
sop for Operation of Fire- Extinguisher
sop for Passivation of WFI Distribution Loop
sop for Analysis of Effluent Treatment Plant Water
sop for Methodology to Dispose ETP Sludge
sop for Action Plan In Case Of Electrical Power Failure
sop for Colour Coding of Piping and Accessories of Utilities
sop for Disposal of Engineering Waste
Filter Cleaning of HVAC System RLAF & LAF
Procedure for Calibration of Magnehelic Gauge
Procedure for Calibration of Vacuum Gauge
Procedure for Calibration of Pressure Gauge
sop for Procedure for Calibration of Temperature Controller
sop for Preventive Maintenance of Infrared Dryer Umbrella Type
sop for Preventive Maintenance of Battery stacker
sop for Preventive Maintenance of Lift
sop for Preventive Maintenance of Vacuum Cleaner
sop for Preventive Maintenance of laminar air flow unit
sop for Preventive Maintenance of Lozenges Manufacturing Line
sop for Preventive Maintenance of Garment Washing Machine
sop for Preventive Maintenance of Multi Column Distillation Plant
sop for Preventive Maintenance of Steam Sterilizer Autoclave
sop for Preventive Maintenance of Pure steam Generator
sop for Preventive maintenance of Depyrogenating Tunnel
sop for Preventive Maintenance of vial sealing machine
sop for preventive maintenance of Powder Filling and Rubber Stoppering machine
sop for Preventive Maintenance of Vial Washing Machine
sop for Preventive Maintenance of Inspection Table
sop for Preventive Maintenance of Hi-Cart
sop for Preventive Maintenance of Turn table
sop for Preventive Maintenance of sticker labeling machine
sop for Preventive Maintenance of Liquid Filling and Sealing Machine
sop for Preventive Maintenance of Linear Bottle Washing Machine
sop for Preventive Maintenance of De-Foiling Machine
sop for Preventive Maintenance of Strip Packing Machine
sop for Preventive Maintenance of Blister Packing Machine
sop for Preventive Maintenance of Capsule Polishing and Sorting Machine
sop for Preventive Maintenance of Capsule Filling Machine
sop for Preventive maintenance of Auto Coater
sop for Preventive Maintenance of Compression Machine
sop for preventive maintenance of packing conveyor belt
sop for Preventive Maintenance of Sifter Cum Multi mill
sop for Preventive Maintenance of Rapid Mixer Granulator
sop for Preventive Maintenance Of Fluid Bed Dryer
sop for Preventive Maintenance of Octagonal Blender
sop for Preventive Maintenance of Lifting and Positioning Device
sop for Preventive Maintenance of Paste Preparation vessel
sop for preventive maintenance of Vibro-Sifter
sop for preventive maintenance of air curtain
sop for preventive maintenance of air handling units