Descaling of Multi Effect Distillation System and Pure Steam Generator
1.0 OBJECTIVE :
1.1 To lay down a procedure for Descaling of Multi Effect Distillation System and Pure Steam Generator .
2.0. SCOPE :
2.1 This procedure is applicable to Multi Effect Distillation System and Pure Steam Generator situated at Pharma Dekho.
3.0. RESPONSIBILITY :
3.1 Operator Engineering Department shall be responsible for Descaling of Multi Effect Distillation System and Pure Steam Generator and maintaining the record.
3.2 Officer/Executive Engineering Department shall be responsible for to verify the proper Descaling of Multi Effect Distillation System and Pure Steam Generator and to take corrective action if any operational deviation.
4.0. ACCOUNTABILITY :
4.1 Head Engineering Department shall be responsible for compliance of SOP.
5.0. PROCEDURE :
5.1 DE SCALING OF COLUMN
5.1.1. Before starting the process switch ‘OFF’ the main control panel of the MEDS and PSG.
5.1.2. Connect the feed water pump suction with the out let of the last column to chemical preparation Stainless Steel (SS) tank..
5.1.3. Add 6 kg sodium hydroxide flakes and 200 liter purified water in chemical tank. Mix the solution properly.
5.1.4. Re-circulate the solution through the columns for 2 hrs by switch ON the feed water pump.
5.1.5. After 2 hours switch ‘Off’ the pump. Drain the solution and flush the column with purified water for neutralizing the system. (Check the pH, it should be7-8).
5.1.6. After neutralization of column, add 30 kg citric acid and 200 liter purified water in chemical tank and mixes the solution properly.
5.1.7. Re-circulate the solution through the columns for 1hr by switch ‘On’ the feed water pump.
5.1.8. After one hour, mix 9 kg Ammonic Bifloride into the citric acid solution and continue the re circulation for another 2 hours.
5.1.9. After the 2 hour re circulation, mix 60 liters of Ammonia solution (commercial grade) and 1 liter Teepol into the citric acid Ammonic Bifloride solution. Continue the re circulation for 2 hours.
5.1.10. After 2 hours re circulation mix 1.5 kg of Sodium Nitrite into the above solution and re circulate for another one hour.
5.1.11. Switch ‘Off’ the feed pumps and drain the solution from the columns.
5.1.12. Flush the columns with purified water for 5-6 hours.
5.1.13. After flushing the columns, check the pH and conductivity. It should be same as feed water. Otherwise continue the flushing till achieved the pH and conductivity.
5.1.14. Reconnect the feed pump suction line and outlet line of the last column.
5.2. DESCALING OF TOP COOLER (CONDENSOR):
5.2.1 Connect the cooling water pump suction and out let of the top cooler to chemical preparation SS tank.
5.2.2 Add5 kg sulphamic acid (commercial grade) and 200-liter warm purified water in chemical tank. Mix the solution properly.
5.2.3 Circulate the solution through the top cooler for 2 hrs by switch ON the cooling water pump.
5.2.4 After 2 hours switch ‘Off’ the pump. Drain the solution and flush the top cooler with purified water for 4-5 hours.
5.2.5 After flushing check the pH and conductivity of the water. It should be same as feed purified water. Otherwise continue the flushing till achieved pH and conductivity.
5.2.6 Reconnect the feed pump suction line and outlet line of the top cooler.
5.2.7 Operate the plant as per SOP No.:
5.2.8 Record the De scaling of MEDS and PSG plant as per Annex –I.
5.2.9 De scaling of the Multi Effect Distillation System and Pure Steam Generator shall be carried out once a year.
6.0. ABBREVIATION :
Sr. No. | Abbreviation used | Full form of abbreviation used |
1. | SOP | Standard operating procedure |
2. | EM | Engineering and maintenance |
3 | MEDS | Multi Effect Distillation System |
4 | PSG | Pure Steam Generator |
ATTACHMENTS (ANNEXES) :
Annex-I : De scaling record of MEDS and PSG plant.
8.0. REFERENCE :
In House
Annex-I : De scaling record of MEDS and PSG plant
sop for Execution of Preventive Maintenance
Preparation of Sodium Hydroxide Solution
sop for water cooled chiller operation
cleaning and preventive maintenance of LAF and RLAF
sop for replacement of water system filters
cleaning and preventive maintenance of insectocutor
sop for operation of preventive maintenance
sop for material receiving and consumption record
sop for Preventive maintenance of bottle washing machine
sop for Replacement of Battery of Electronic Devices
sop for Preparation of R.O. Antiscalant Solution
Preventive Maintenance of Rapid Cooling Steam Sterilizer
Preventive Maintenance of Rapid cooling steam Generator
sop for Preventive Maintenance of Dust Collector
sop for Replacement of HVAC filters
SOP for Battery Backup in Mobile Laminar Air Flow Trolley
sop for Replacement of Tube lights
sop for Replacement of UV light of purified water plant
sop for Cleaning of soft water storage tank and RO feed tank
sop for Preparation of Sodium hydroxide Solution
sop for Operation and regeneration of softener plant
Procedure Of Issuance Of material from Engineering Store
sop for Preventive Maintenance of Filter Press
sop for Preventive Maintenance of Sugar Transfer System
sop for Preventive Maintenance of Shrink Sleeve Machine
sop for Preventive Maintenance of ROPP Cap Elevator
sop for Preventive Maintenance of Liquid Transfer Pumps
sop for Preventive Maintenance of Liquid Tanks
Preventive Maintenance of Strip De-Foiling Machine
sop for Preventive Maintenance of Colloidal Mill
sop for Preventive Maintenance of Packing Collator Belt
sop for Checking light intensity
sop for Operation of Fire- Extinguisher
sop for Passivation of WFI Distribution Loop
sop for Analysis of Effluent Treatment Plant Water
sop for Methodology to Dispose ETP Sludge
sop for Action Plan In Case Of Electrical Power Failure
sop for Colour Coding of Piping and Accessories of Utilities
sop for Disposal of Engineering Waste
Filter Cleaning of HVAC System RLAF & LAF
Procedure for Calibration of Magnehelic Gauge
Procedure for Calibration of Vacuum Gauge
Procedure for Calibration of Pressure Gauge
sop for Procedure for Calibration of Temperature Controller
sop for Preventive Maintenance of Infrared Dryer Umbrella Type
sop for Preventive Maintenance of Battery stacker
sop for Preventive Maintenance of Lift
sop for Preventive Maintenance of Vacuum Cleaner
sop for Preventive Maintenance of laminar air flow unit
sop for Preventive Maintenance of Lozenges Manufacturing Line
sop for Preventive Maintenance of Garment Washing Machine
sop for Preventive Maintenance of Multi Column Distillation Plant
sop for Preventive Maintenance of Steam Sterilizer Autoclave
sop for Preventive Maintenance of Pure steam Generator
sop for Preventive maintenance of Depyrogenating Tunnel
sop for Preventive Maintenance of vial sealing machine
sop for preventive maintenance of Powder Filling and Rubber Stoppering machine
sop for Preventive Maintenance of Vial Washing Machine
sop for Preventive Maintenance of Inspection Table
sop for Preventive Maintenance of Hi-Cart
sop for Preventive Maintenance of Turn table
sop for Preventive Maintenance of sticker labeling machine
sop for Preventive Maintenance of Liquid Filling and Sealing Machine
sop for Preventive Maintenance of Linear Bottle Washing Machine
sop for Preventive Maintenance of De-Foiling Machine
sop for Preventive Maintenance of Strip Packing Machine
sop for Preventive Maintenance of Blister Packing Machine
sop for Preventive Maintenance of Capsule Polishing and Sorting Machine
sop for Preventive Maintenance of Capsule Filling Machine
sop for Preventive maintenance of Auto Coater
sop for Preventive Maintenance of Compression Machine
sop for preventive maintenance of packing conveyor belt
sop for Preventive Maintenance of Sifter Cum Multi mill
sop for Preventive Maintenance of Rapid Mixer Granulator
sop for Preventive Maintenance Of Fluid Bed Dryer
sop for Preventive Maintenance of Octagonal Blender
sop for Preventive Maintenance of Lifting and Positioning Device
sop for Preventive Maintenance of Paste Preparation vessel
sop for preventive maintenance of Vibro-Sifter
sop for preventive maintenance of air curtain
sop for preventive maintenance of air handling units
Preventive Maintenance of Diesel Generator
sop for Preventive Maintenance of cooling towers
sop for Preventive Maintenance of Boiler
sop for Preventive Maintenance of Air Compressor
sop for Preventive Maintenance of Chilling Plant
sop for Preventive Maintenance of Transformers
sop for Preventive maintenance of Purified Water System
sop for Break Down maintenance of Machine and Work Requisition