Site icon Pharma Dekho

Operation and Sanitization of Multi Grade filter

 

Operation and Sanitization of Multi Grade filter

 

1.0 OBJECTIVE :

1.1 To lay down a procedure for Operation and Sanitization of Multi Grade filter.

2.0. SCOPE :

2.1 This procedure is applicable for Multi Grade Filter situated at Pharma Dekho

3.0. RESPONSIBILITY :

3.1 Operator Engineering Department shall be responsible for operation and Sanitization of Multi Grade Filter and maintaining the cleaning records.
3.2 Officer/Executive Engineering Department shall be responsible to verify the proper Multi Grade Filter.

4.0. ACCOUNTABILITY :
4.1. Head Engineering Department shall be accountable for compliance of SOP.

5.0. PROCEDURE :
5.1. Operation And Sanitization Of Multi Grade Filter
5.1.1 Start up:
5.1.1 Before starting the plant, ensure that the water inlet valve and outlet valve are open.
5.1.2 Switch ‘On’ the raw water feed pump.
5.1.3 Check the inlet pressure and outlet pressure; Inlet pressure should not be less than 3 kg/cm2 and outlet pressure 2.5 kg/cm2. If pressure drop is more than 0.5 kg/cm2, backwash the unit as per the back wash procedure.



5.1.2 Backwash:
5.1.1 Select the valve position to backwash and continuo the washing for the specified limit (10 min.) or till the effluent is clear, after complete the backwash process selects the valve position to filter for normal operation. Then close wash outlet valve and wash inlet valve.
5.1.2 Open inlet Valve and drain valve, Check the clarity of the drain water, if clear                 close drain valve and open outlet valve.
5.1.3 Maintain the record of backwash and rinse of Multi Grade filter on daily basis as               per Annex-III.
5.1.3 Replacement of filtering sand:
5.1.3.1 Replacement of filtering sand to be carried out once in eighteen months for better performance of the system as per SOP No.1EM-010.
5.1.4 Cleaning Of Multi Grade Filter
5.1.4.1 Open the strainer filter top and bottom.
5.1.4.2 Remove sand and stone from bottom and collect in the tank.
5.1.4.3 Clean the sand stone with10 lit solution of 5% NAOH and keep it for 30 minutes.
5.1.4.4 Close the bottom of strainer and put stone one by one and sand.
5.1.4.5 Close the top of strainer and operate as per step 5.1.1 to 5.1.3.
5.1.4.6 Frequency multi grade filters cleaning in quarterly and maintain a record of cleaning record in Annex- I.
5.2 Sanitization Of Multi Grade Filter
5.2.1 Back wash the filter plants with potable water.
5.2.2 Take 1000 liters of 1% sodium hypochloride solution in the potable water storage tank.
5.2.3 Connect the out let of the multi grade Filter to tank by PVC flexible tube.
5.2.4 before starting the solution feed pump, keep the inlet and outlet valves of Multi Grade Filter open.
5.2.5 Switch ON the feed pump.
5.2.6 keep the discharge valve in throttle position till the chemical solution comes out from the Multi Grade filter.
5.2.7 Displace the water from the filters to drain, then enroute the solution back to the solution tank.



5.2.8 After injection, soak the solution for one an hour by switch OFF the pump.
5.2.9 After the specified time, restart the pump and re circulate the solution for one hour.
5.2.10 After one hour, switch OFF the pump and drain out the solution by opening the drain valves.
5.2.11 Then close the drain valve and collect the fresh water in the tank.
5.2.12 Flush out the plant by switch ON the feed pump for one an hour.
5.2.13 Check the sample for residual free chlorine. If the sample found OK, Start Multi Grade Filter, Otherwise
continue the flushing till get traces free water.
5.2.14 Sanitization of Multi Grade Filter shall be carried out once in six months.
5.2.15 Maintain the record of sanitization of Multi Grade filter on half yearly basis as par Annex –II.

6.0. ABBREVIATION :

Sr. No. Abbreviation used Full form of abbreviation used
1. SOP Standard operating procedure

ATTACHMENTS (ANNEXES) :

Annex-I: Cleaning Record for Multi Grade Filter
Annex-II: Record of sanitization of Multi Grade filter
Annex-III: Record of backwash and rinse of Multi Grade filter

8.0.      REFERENCE :

In House

Annex-I: Cleaning Record for Multi Grade Filter

Annex-II: Record of sanitization of Multi Grade filter

Annex-III: Record of backwash and rinse of Multi Grade filter

 

sop for Execution of Preventive Maintenance

Preparation of Sodium Hydroxide Solution

sop for Breakdown Maintenance

sop for Handling of Filters

sop for water cooled chiller operation

cleaning and preventive maintenance of LAF and RLAF

sop for replacement of water system filters

cleaning and preventive maintenance of insectocutor

sop for operation of preventive maintenance

sop for material receiving and consumption record

sop for Preventive maintenance of bottle washing machine

sop for Replacement of Battery of Electronic Devices

sop for Preparation of R.O. Antiscalant Solution

Preventive Maintenance of Rapid Cooling Steam Sterilizer

Preventive Maintenance of Rapid cooling steam Generator

sop for Preventive Maintenance of Dust Collector

sop for Replacement of HVAC filters

SOP for Battery Backup in Mobile Laminar Air Flow Trolley

sop for Replacement of Tube lights

sop for Replacement of UV light of purified water plant

sop for Cleaning of soft water storage tank and RO feed tank

sop for Preparation of Sodium hydroxide Solution

sop for Operation and regeneration of softener plant

Procedure Of Issuance Of material from Engineering Store

sop for Preventive Maintenance of Filter Press

sop for Preventive Maintenance of Sugar Transfer System

sop for Preventive Maintenance of Shrink Sleeve Machine

sop for Preventive Maintenance of ROPP Cap Elevator

sop for Preventive Maintenance of Liquid Transfer Pumps

sop for Preventive Maintenance of Liquid Tanks

Preventive Maintenance of Strip De-Foiling Machine

sop for Preventive Maintenance of Colloidal Mill

sop for Preventive Maintenance of Packing Collator Belt

sop for Checking light intensity

sop for Operation of Fire- Extinguisher

sop for Passivation of WFI Distribution Loop

sop for Analysis of Effluent Treatment Plant Water

sop for Methodology to Dispose ETP Sludge

sop for Action Plan In Case Of Electrical Power Failure

sop for Colour Coding of Piping and Accessories of Utilities

sop for Replacement Policy

sop for Disposal of Engineering Waste

Filter Cleaning of HVAC System RLAF & LAF

Procedure for Calibration of Magnehelic Gauge

Procedure for Calibration of Vacuum Gauge

Procedure for Calibration of Pressure Gauge

sop for Procedure for Calibration of Temperature Controller

sop for Area Validation

sop for Preventive Maintenance of Infrared Dryer Umbrella Type

sop for Preventive Maintenance of Battery stacker

sop for Preventive Maintenance of Lift

sop for Preventive Maintenance of Vacuum Cleaner

sop for Preventive Maintenance of laminar air flow unit

sop for Preventive Maintenance of Lozenges Manufacturing Line

sop for Preventive Maintenance of Garment Washing Machine

sop for Preventive Maintenance of Multi Column Distillation Plant

sop for Preventive Maintenance of Steam Sterilizer Autoclave

sop for Preventive Maintenance of Pure steam Generator

sop for Preventive maintenance of Depyrogenating Tunnel

sop for Preventive Maintenance of vial sealing machine

sop for preventive maintenance of Powder Filling and Rubber Stoppering machine

sop for Preventive Maintenance of Vial Washing Machine

sop for Preventive Maintenance of Inspection Table

sop for Preventive Maintenance of Hi-Cart

sop for Preventive Maintenance of Turn table

sop for Preventive Maintenance of sticker labeling machine

sop for Preventive Maintenance of Liquid Filling and Sealing Machine

sop for Preventive Maintenance of Linear Bottle Washing Machine

sop for Preventive Maintenance of De-Foiling Machine




sop for Preventive Maintenance of Strip Packing Machine

sop for Preventive Maintenance of Blister Packing Machine

sop for Preventive Maintenance of Capsule Polishing and Sorting Machine

sop for Preventive Maintenance of Capsule Filling Machine 

sop for Preventive maintenance of Auto Coater

sop for Preventive Maintenance of Compression Machine

sop for preventive maintenance of packing conveyor belt

sop for Preventive Maintenance of Sifter Cum Multi mill

sop for Preventive Maintenance of Rapid Mixer Granulator

sop for Preventive Maintenance Of Fluid Bed Dryer

sop for Preventive Maintenance of Octagonal Blender

sop for Preventive Maintenance of Lifting and Positioning Device

sop for Preventive Maintenance of Paste Preparation vessel

sop for preventive maintenance of Vibro-Sifter

sop for preventive maintenance of air curtain

sop for preventive maintenance of air handling units

Preventive Maintenance of Diesel Generator

sop for Preventive Maintenance of cooling towers

sop for Preventive Maintenance of Boiler

sop for Preventive Maintenance of Air Compressor

sop for Preventive Maintenance of Chilling Plant

sop for Preventive Maintenance of Transformers

sop for Preventive maintenance of Purified Water System

sop for Break Down maintenance of Machine and Work Requisition

sop for Building Maintenance

sop for Operation of Lift

sop for Operation of Dust Extraction System

sop for Operation Of Effluent Treatment Plant

sop for Operation Of Diesel Generator

sop for Operation of Multi Column Distillation Plant

sop for Operation of Pure Steam Generator

sop for Operation of Air Handling Unit

sop for Operation of Cooling Tower

sop for Operation of Air Compressor

sop for Operation of Water Chilling Plant

sop for Operation of Boiler

sop for Cleaning of Pure Steam Generator

Cleaning of Over Head Water Tanks HDPE

sop for Cleaning of Water tanks

sop for Sanitization of multi column plant

sop for Sanitization of Ultrafiltration System

Sop for Chemical Sanitization of Reverse Osmosis

Sop for Sanitization of Hot Sanitization & Electro Deionization unit

sop for Sanitization of Purified Water Loop

sop for preparation of sodium meta bisulphate solution

sop for Testing of Hardness of Soft Water

sop for Operation & back wash of multi grade filter