sop for Operation of Boiler
1.0 Objective
To lay down a procedure for Operation of Boiler
2.0 Scope
This Standard Operating Procedure is applicable for Operation of Boiler (Make: Forbes Marshall, Capacity 4500 Kg/hr) to be followed at formulation plants
3.0 Responsibility
3.1 Engineering Officer / Executive shall be responsible for the execution of this procedure.
3.2 Engineering Manager shall be responsible for the implementation of this SOP.
3.3 Head QA/designee shall be responsible for the compliance of this SOP.
4.0 Abbreviations and Definitions
SOP : Standard Operating Procedure etc
QA : Quality assurance
Ppm : Parts per million
kg/cm² : Kilo grams per Centimeter square
°C : Degree Celsius
ER : Engineering
TDS : Total Dissolved Solid
NMT : Not More Than
FO : Furnace oil
MCB : Miniature circuit Breaker
MCCB : Miniature Control circuit Breaker
HSD : High Speed Diesel
5.0 Procedure
5.1 Operation of boiler shall be carried out as per the requirement.
5.2 Boiler start and stop operation shall be performed as per the instruction from engineering Officer.
5.3 Operation of boiler:
5.3.1 Boiler can be operated with both FO and Diesel
5.3.2 Check the feed water quality. It shall be as follows.
5.3.2.1 Hardness – Less than5 PPM.
5.3.2.2 PH – Between 8.0 to 9.0
5.3.2.3 TDS- NMT 300PPM for feed water
5.3.2.4 TDS- NMT 3500 PPM For boiler blow down water
5.4 Operation Using FO
5.4.1 Check the level of boiler feed water tank and furnace oil day tank. Level shall be maintained above half level of the tank capacity in both feed water tank and furnace oil in Day Tank.
5.4.2 Open the outlet valve of boiler feed water tank and Furnace oil day tank.
5.4.3 Switch on MCCB, mounted on Boiler main panel & Switch on the MCB of Furnace oil day tank heater from boiler main panel.
5.4.4 FO day tank temperature should be in between 70-90oC .If temperature attains more than 90oC then switch off the MCB mounted on boiler panel for the power supply of Heaters.
5.4.5 Check water level Indicator (Gauge Glass) on water level indicator mounted on the boiler. It shall be always in between high and low levels marked on the level indicator sight glass.
5.4.6 Turn the selector switch and select Feed water pump no. 1 or 2 .Then put selector Switch marked as “F.P Control switch” in Auto mode.
5.4.7 Start main furnace oil pump.
5.4.8 Check that temperature setting of furnace oil is in between 100ºC to 120ºC, which can be seen by thermostat on temp controller.
5.4.9 Ensure the temperature setting of furnace oil is 100ºC cut-in and 125ºC cut – off mounted on boiler panel .Which can be seen by temperature indicator and controller.
5.4.10 Turn the selector switch to “ON” position mounted on boiler panel marked as “Heater ON/OFF”.
5.4.11 Turn the purging level to ‘P’ position i.e. to purging for 5 minutes.
5.4.12 Turn the burner ON/OFF selector switch mounted on boiler panel to ON position.
5.4.13 Turn the selector level to ‘A’ position i.e. in Auto Mode. Heater will cut off when FO temperature reaches below or above the set temperature. Boiler will restart after few seconds and boiler goes in firing mode.
5.4.14 Ensure that flame is established, which can be seen by view panel.
5.4.15 If not then boiler will go into the lock-out mode. Reset boiler by pressing push button.
5.4.16 Check that the steam pressure in the boiler is minimum 1.0 Kg/cm2. If it is less then open air relief valve.
5.4.17 Turn the firing rate control switch to low firing for 10 Min.
5.4.18 After 10 min, turn firing rate control switch to medium firing for 10min.
5.4.19 Close Air relief valve mounted above the boiler after steam pressure attends1.0Kg/cm².
5.4.20 Open steam stop valve when pressure gauge shows 5 Kg/cm2.
5.4.21 Turn firing rate control switch to “Auto mode” after one normal cut off by steam pressure switch.
5.4.22 Open blow down valve for 30-40 seconds after every 8 Hours of operation.
5.4.23 Drain water level indicator gauge glass after every operation of 8 Hours.
5.4.24 Drain mobbery water for 15 to 20 second by drain valve after every operation of 8 hours.
5.5 Stopping Procedure
5.5.1 Turn off the burner switch.
5.5.2 Switch off furnace oil circulation pump.
5.5.3 Switch off furnace oil preheated.
5.5.4 Maintain 80% water level in gauge glass which can be seen in water level Indicator.
5.5.5 Operate blow down valve for 30-40 seconds approx.
5.5.6 Drain mobbery water.
5.5.7 Close main steam stop valve. Water level should be 60-80% shown in water level Indicator.
5.5.8 Switch off main power supply which is mounted on boiler panel.
5.6 Operation Using Diesel
5.6.1 Check the level of boiler feed water tank and HSD oil tank. Level shall be maintained above half level of the tank capacity in both feed water tank and HSD oil in Day Tank
5.6.2 Open the outlet valve of boiler feed water tank and HSD oil Tank.
5.6.3 Ensure HSD day tank temperature should be between 10ºC – 15ºC.
5.6.4 Start main HSD oil pump.
5.6.5 Turn the selector switch on for firing.
5.6.6 At the time of this period oil heater should be switched off.
5.6.7 HSD temp should be maintained between 15 ºC – 25 ºC.
5.7 Stopping Procedure.
5.7.1 Turn off the burner switch.
5.7.2 Switch off HSD circulation pump.
5.7.3 Switch off Pre-heater.
5.7.4 Maintain 80% water level in gauge glass.
5.7.5 Operate blow down valve up to 30 to 40 seconds approx.
5.7.6 Drain mobbrey water.
5.7.7 Close main steam valve.
5.7.8 Switch off main power supply which is mounted on boiler panel.
5.8 Note down the operation parameter as per format no.
6.0 Forms and Records
6.1 Boiler Operation record – Annexure-1
7.0 Distribution
7.1 Master copy – Documentation Cell (Quality Assurance)
7.2 Controlled copies – Engineering Department
sop for Execution of Preventive Maintenance
Preparation of Sodium Hydroxide Solution
sop for water cooled chiller operation
cleaning and preventive maintenance of LAF and RLAF
sop for replacement of water system filters
cleaning and preventive maintenance of insectocutor
sop for operation of preventive maintenance
sop for material receiving and consumption record
sop for Preventive maintenance of bottle washing machine
sop for Replacement of Battery of Electronic Devices
sop for Preparation of R.O. Antiscalant Solution
Preventive Maintenance of Rapid Cooling Steam Sterilizer
Preventive Maintenance of Rapid cooling steam Generator
sop for Preventive Maintenance of Dust Collector
sop for Replacement of HVAC filters
SOP for Battery Backup in Mobile Laminar Air Flow Trolley
sop for Replacement of Tube lights
sop for Replacement of UV light of purified water plant
sop for Cleaning of soft water storage tank and RO feed tank
sop for Preparation of Sodium hydroxide Solution
sop for Operation and regeneration of softener plant
Procedure Of Issuance Of material from Engineering Store
sop for Preventive Maintenance of Filter Press
sop for Preventive Maintenance of Sugar Transfer System
sop for Preventive Maintenance of Shrink Sleeve Machine
sop for Preventive Maintenance of ROPP Cap Elevator
sop for Preventive Maintenance of Liquid Transfer Pumps
sop for Preventive Maintenance of Liquid Tanks
Preventive Maintenance of Strip De-Foiling Machine
sop for Preventive Maintenance of Colloidal Mill
sop for Preventive Maintenance of Packing Collator Belt
sop for Checking light intensity
sop for Operation of Fire- Extinguisher
sop for Passivation of WFI Distribution Loop
sop for Analysis of Effluent Treatment Plant Water
sop for Methodology to Dispose ETP Sludge
sop for Action Plan In Case Of Electrical Power Failure
sop for Colour Coding of Piping and Accessories of Utilities
sop for Disposal of Engineering Waste
Filter Cleaning of HVAC System RLAF & LAF
Procedure for Calibration of Magnehelic Gauge
Procedure for Calibration of Vacuum Gauge
Procedure for Calibration of Pressure Gauge
sop for Procedure for Calibration of Temperature Controller
sop for Preventive Maintenance of Infrared Dryer Umbrella Type
sop for Preventive Maintenance of Battery stacker
sop for Preventive Maintenance of Lift
sop for Preventive Maintenance of Vacuum Cleaner
sop for Preventive Maintenance of laminar air flow unit
sop for Preventive Maintenance of Lozenges Manufacturing Line
sop for Preventive Maintenance of Garment Washing Machine
sop for Preventive Maintenance of Multi Column Distillation Plant
sop for Preventive Maintenance of Steam Sterilizer Autoclave
sop for Preventive Maintenance of Pure steam Generator
sop for Preventive maintenance of Depyrogenating Tunnel
sop for Preventive Maintenance of vial sealing machine
sop for preventive maintenance of Powder Filling and Rubber Stoppering machine
sop for Preventive Maintenance of Vial Washing Machine
sop for Preventive Maintenance of Inspection Table
sop for Preventive Maintenance of Hi-Cart
sop for Preventive Maintenance of Turn table
sop for Preventive Maintenance of sticker labeling machine
sop for Preventive Maintenance of Liquid Filling and Sealing Machine
sop for Preventive Maintenance of Linear Bottle Washing Machine
sop for Preventive Maintenance of De-Foiling Machine
sop for Preventive Maintenance of Strip Packing Machine
sop for Preventive Maintenance of Blister Packing Machine
sop for Preventive Maintenance of Capsule Polishing and Sorting Machine
sop for Preventive Maintenance of Capsule Filling Machine
sop for Preventive maintenance of Auto Coater
sop for Preventive Maintenance of Compression Machine
sop for preventive maintenance of packing conveyor belt
sop for Preventive Maintenance of Sifter Cum Multi mill
sop for Preventive Maintenance of Rapid Mixer Granulator
sop for Preventive Maintenance Of Fluid Bed Dryer
sop for Preventive Maintenance of Octagonal Blender
sop for Preventive Maintenance of Lifting and Positioning Device
sop for Preventive Maintenance of Paste Preparation vessel
sop for preventive maintenance of Vibro-Sifter
sop for preventive maintenance of air curtain
sop for preventive maintenance of air handling units
Preventive Maintenance of Diesel Generator
sop for Preventive Maintenance of cooling towers
sop for Preventive Maintenance of Boiler
sop for Preventive Maintenance of Air Compressor
sop for Preventive Maintenance of Chilling Plant
sop for Preventive Maintenance of Transformers
sop for Preventive maintenance of Purified Water System
sop for Break Down maintenance of Machine and Work Requisition
sop for Operation of Dust Extraction System
sop for Operation Of Effluent Treatment Plant
sop for Operation Of Diesel Generator
sop for Operation of Multi Column Distillation Plant
sop for Operation of Pure Steam Generator
sop for Operation of Air Handling Unit
sop for Operation of Cooling Tower
sop for Operation of Air Compressor
sop for Operation of Water Chilling Plant
sop for Cleaning of Pure Steam Generator
Cleaning of Over Head Water Tanks HDPE
sop for Cleaning of Water tanks
sop for Sanitization of multi column plant
sop for Sanitization of Ultrafiltration System
Sop for Chemical Sanitization of Reverse Osmosis
Sop for Sanitization of Hot Sanitization & Electro Deionization unit
sop for Sanitization of Purified Water Loop
sop for preparation of sodium meta bisulphate solution
sop for Testing of Hardness of Soft Water