1.0 Objective 
To lay down a procedure for the operation of AHU system, Ventilation& Exhaust System.
2.0 Scope
This Standard Operating Procedure is applicable for the operation of all Air Handling Unit (Make Contec Air Flow) to be followed at formulation plants
3.0 Responsibility
3.1 Engineering Officer / Executive shall be responsible for the execution of this procedure.
3.2 Engineering Manager shall be responsible for the implementation of this SOP.
3.3 Head QA/designee shall be responsible for the compliance of this SOP.
4.0 Abbreviations and Definitions
SOP : Standard Operating Procedure
No : Number
QA : Quality assurance
Qty : Quantity
AHU : Air handling unit
CHW : Chilled water
ER : Engineering
VFD : Variable Frequency Drive


5.0 Procedure.
5.1 Check for availability of power supply in all AHU main panel and individual AHU Panel.
5.2 Check that the doors are completely closed to avoid any leakage of air.
5.3 Check that the fresh air damper.
5.4 Check that the CHW (chilled water) inlet and CHW outlet.
5.5 Ensure that 3-way valve in return circuit of chilled water is adequately opened and by-pass valve is closed. By pass valve is operated in case only when 3-way valve is taken for preventive maintenance/breakdown maintenance.
5.6 Check that the chiller plant is continuously operated for provision of chilled water to the AHU at not more than 20ºC.
5.7 Check that the pressure gauges and temperature gauges are properly mounted.
5.8 After ensuring all above points. Switch on the AHU from the AHU panel.
5.9 Check Magnehalic gauge readings for pressure difference across pre filter (4 to 8 mm WC) and fine filters (8 to 12 mm WC) and note down the reading in log book.
5.10 Check Magnehalic gauge readings for pressure difference across HEPA filter (25 to 50 mm WC) and note down the reading in log book.
5.11 If readings are below limit replace filter and if it is above limit clean the filter.
5.12 Before shutdown of the AHU ensure the pressure difference across pre filter (4 to 8 mm WC) and fine filters (8 to 12 mm WC) are maintained and record the same in AHU operation log.
5.13 If the area is under cleaning temperature, RH & differential pressure shall not be recorded at the time. Production in charge will ensure that the required environment condition are maintained before the start of production which shall be recorded in the BMR, in case of any deviation he will inform engineering department immediately for corrective action.
5.14 At the start of shift / day, AHU of all Corridors shall be started first. Afterwards other AHUs shall be started. In case of power failure and after its restoration through DG power ensure that AHUs of all passage / corridor starts in auto mode first. This is to prevent cross contamination. All other AHU’S are then started one by one in manual mode of operation. Production in-charge will ensure that the required environmental parameters are achieved before re-commencement of production activity. In dry powder injection, all AHUs will start in auto mode. HVAC operator will log the stop and start status of AHU’s in Annexure-1
5.15 In case AHU fails to start after power restoration due to any reason/fault, HVAC operator will immediately informed Engineering Manager who will confirm precautionary measures to production department. After rectification of fault, HVAC engineer will inform the production charge so that the production activities can be re-started again.



6.0 Forms and Records
6.1 Air Handling Unit Operation Records. – Annexure-1
7.0 Distribution
7.1 Master copy – Documentation Cell (Quality Assurance)
7.2 Controlled copies – Engineering Department

Annexure-1

 sop for Execution of Preventive Maintenance

Preparation of Sodium Hydroxide Solution

sop for Breakdown Maintenance

sop for Handling of Filters

sop for water cooled chiller operation

cleaning and preventive maintenance of LAF and RLAF

sop for replacement of water system filters

cleaning and preventive maintenance of insectocutor

sop for operation of preventive maintenance

sop for material receiving and consumption record

sop for Preventive maintenance of bottle washing machine

sop for Replacement of Battery of Electronic Devices

sop for Preparation of R.O. Antiscalant Solution

Preventive Maintenance of Rapid Cooling Steam Sterilizer

Preventive Maintenance of Rapid cooling steam Generator

sop for Preventive Maintenance of Dust Collector

sop for Replacement of HVAC filters

SOP for Battery Backup in Mobile Laminar Air Flow Trolley

sop for Replacement of Tube lights

sop for Replacement of UV light of purified water plant

sop for Cleaning of soft water storage tank and RO feed tank

sop for Preparation of Sodium hydroxide Solution

sop for Operation and regeneration of softener plant

Procedure Of Issuance Of material from Engineering Store

sop for Preventive Maintenance of Filter Press

sop for Preventive Maintenance of Sugar Transfer System

sop for Preventive Maintenance of Shrink Sleeve Machine

sop for Preventive Maintenance of ROPP Cap Elevator

sop for Preventive Maintenance of Liquid Transfer Pumps

sop for Preventive Maintenance of Liquid Tanks

Preventive Maintenance of Strip De-Foiling Machine

sop for Preventive Maintenance of Colloidal Mill

sop for Preventive Maintenance of Packing Collator Belt

sop for Checking light intensity

sop for Operation of Fire- Extinguisher

sop for Passivation of WFI Distribution Loop

sop for Analysis of Effluent Treatment Plant Water

sop for Methodology to Dispose ETP Sludge

sop for Action Plan In Case Of Electrical Power Failure

sop for Colour Coding of Piping and Accessories of Utilities

sop for Replacement Policy

sop for Disposal of Engineering Waste

Filter Cleaning of HVAC System RLAF & LAF

Procedure for Calibration of Magnehelic Gauge

Procedure for Calibration of Vacuum Gauge

Procedure for Calibration of Pressure Gauge

sop for Procedure for Calibration of Temperature Controller

sop for Area Validation

sop for Preventive Maintenance of Infrared Dryer Umbrella Type

sop for Preventive Maintenance of Battery stacker

sop for Preventive Maintenance of Lift

sop for Preventive Maintenance of Vacuum Cleaner

sop for Preventive Maintenance of laminar air flow unit

sop for Preventive Maintenance of Lozenges Manufacturing Line

sop for Preventive Maintenance of Garment Washing Machine

sop for Preventive Maintenance of Multi Column Distillation Plant

sop for Preventive Maintenance of Steam Sterilizer Autoclave

sop for Preventive Maintenance of Pure steam Generator

sop for Preventive maintenance of Depyrogenating Tunnel

sop for Preventive Maintenance of vial sealing machine

sop for preventive maintenance of Powder Filling and Rubber Stoppering machine

sop for Preventive Maintenance of Vial Washing Machine

sop for Preventive Maintenance of Inspection Table

sop for Preventive Maintenance of Hi-Cart

sop for Preventive Maintenance of Turn table

sop for Preventive Maintenance of sticker labeling machine

sop for Preventive Maintenance of Liquid Filling and Sealing Machine

sop for Preventive Maintenance of Linear Bottle Washing Machine

sop for Preventive Maintenance of De-Foiling Machine

sop for Preventive Maintenance of Strip Packing Machine

sop for Preventive Maintenance of Blister Packing Machine

sop for Preventive Maintenance of Capsule Polishing and Sorting Machine

sop for Preventive Maintenance of Capsule Filling Machine 

sop for Preventive maintenance of Auto Coater

sop for Preventive Maintenance of Compression Machine

sop for preventive maintenance of packing conveyor belt

sop for Preventive Maintenance of Sifter Cum Multi mill

sop for Preventive Maintenance of Rapid Mixer Granulator

sop for Preventive Maintenance Of Fluid Bed Dryer

sop for Preventive Maintenance of Octagonal Blender

sop for Preventive Maintenance of Lifting and Positioning Device

sop for Preventive Maintenance of Paste Preparation vessel

sop for preventive maintenance of Vibro-Sifter

sop for preventive maintenance of air curtain

sop for preventive maintenance of air handling units

Preventive Maintenance of Diesel Generator

sop for Preventive Maintenance of cooling towers

sop for Preventive Maintenance of Boiler

sop for Preventive Maintenance of Air Compressor

sop for Preventive Maintenance of Chilling Plant

sop for Preventive Maintenance of Transformers

sop for Preventive maintenance of Purified Water System

sop for Break Down maintenance of Machine and Work Requisition

sop for Building Maintenance

sop for Operation of Lift

sop for Operation of Dust Extraction System

sop for Operation Of Effluent Treatment Plant

sop for Operation Of Diesel Generator

sop for Operation of Multi Column Distillation Plant

sop for Operation of Pure Steam Generator

sop for Operation of Air Handling Unit

sop for Operation of Cooling Tower

sop for Operation of Air Compressor

sop for Operation of Water Chilling Plant

sop for Operation of Boiler

sop for Cleaning of Pure Steam Generator

Cleaning of Over Head Water Tanks HDPE

sop for Cleaning of Water tanks

sop for Sanitization of multi column plant

sop for Sanitization of Ultrafiltration System

Sop for Chemical Sanitization of Reverse Osmosis

Sop for Sanitization of Hot Sanitization & Electro Deionization unit

sop for Sanitization of Purified Water Loop

sop for preparation of sodium meta bisulphate solution

sop for Testing of Hardness of Soft Water

sop for Operation & back wash of multi grade filter

sop for testing of chlorine contents in water

Exit mobile version