sop for Breakdown Maintenance
1.0 PURPOSE
To define a procedure for handling of breakdown maintenance of equipment/ instrument.
2.0 SCOPE
2.1 This procedure applies to all the equipments instruments and utility equipments
3.0 REFERENCE
3.1 References
3.1.1 In-House
3.2 ANNEXURE
3.2.1 Annexure-I : Breakdown maintenance intimation slip.
3.2.2 Annexure-II : Log for issuance of Breakdown maintenance serial number.
4.0 ABBREVIATION
4.1 Breakdown Maintenance
Breakdown Maintenance is a set of measures taken to rectify faults that result in the failure of
equipment /instrument and restore it to normal functioning.
4.2 Abbreviations
4.2.1 CAPA: Corrective and Preventive Action
4.2.2 PMF: Planned Modification form
4.2.3 QA: Quality Assurance
4.2.4 SIP: Sterilization In Place
5.0 RESPONSIBILITY
5.1 Corporate Quality Assurance
5.1.1 To ensure the implementation of the procedure.
5.2 Concerned department:
5.2.1 To report the breakdown and label “under breakdown maintenance”.
5.2.2 To intimate the breakdown.
5.2.3 To verify the maintenance status.
5.3 Engineering department
5.3.1 To receive the intimation of breakdown.
5.3.2 To evaluate the reason for breakdown and rectify the problem
5.3.3 To investigate impact analysis of the breakdown, if required.
5.3.4 To maintain the equipment/ instrument history card of respective equipment/ instrument.
5.4 Quality Assurance
5.4.1 To ensure the proper documentation of the breakdown.
5.4.2 To allocate incident number, if required
5.4.3 To allocate the planned modification number, if required.
5.5 QA Head
5.5.1 To investigate impact analysis of the breakdown, if required.
5.5.2 To ensure implementation of defined procedure.
5.6 Plant Head
5.5.1 To investigate impact analysis of the breakdown, if required.
5.5.2 To ensure implementation of defined procedure.
6.0 Distribution:
I. Quality Assurance
II. Quality Control
III. Production
IV. Ware house
V. Engineering
VI. Environment, Health and safety
7.0 PROCEDURE:
7.1 Part-1 (For concerned department)
7.1.1 In case of equipment/instrument breakdown, the concerned department shall label it
with “Under Breakdown Maintenance” status label as per SOP
7.1.2 The concerned department shall fill the Following details in the breakdown maintenance
intimation slip and shall send to QA for evaluation as per Attachment-I (Break down Maintenance slip).
• Sr. No. of breakdown maintenance (Shall be allocated by QA).
• Name, code and location of equipment /instrument which has failed to work/ function.
• Nature of problem.
• Product and batch(s) number under impact.
• Remarks of department head.
• Intimated to QA by and date.
7.1.3 Reference of breakdown maintenance intimation slip serial number shall be entered in
sequential log of equipment / instrument.
7.2 Part-2 (For Quality Assurance)
7.2.1 QA shall allocate the Serial Number as per below system and record in log as per Attachment-II:
BM/YY/B-NNN
Where,
BM stands for Breakdown Maintenance:
YY stands for last two digits of current year, i.e. 20 for year 2020.
B stands for Block i.e.- B1 for Block 1
B2 for Block 2
U for Utility block
Q for Quality control/ Quality Assurance
A for Admin block
7.2.2 Breakdown maintenance serial number shall be maintained block wise at Quality Assurance.
7.2.3 QA shall ensure that proper documentation for the breakdown is done in sequential log of
the equipment /instrument which has failed to work and in relevant batch records.
7.2.4 QA shall allot deviation/incident number and mention in break down intimation slip (Attachment-I).
7.2.5 If required, QA shall give further remarks regarding impact evaluation or any other in addition
to remarks of concerned department head.
7.2.6 QA may hold the product batches if any under impact till further investigation.
7.2.7 After filling of all the details QA shall forward the breakdown maintenance intimation slip to concerned department.
7.3 Part-3 (For concerned department)
7.3.1 Concerned department shall acknowledge the comments of QA and initiate for the further
actions required which may be preparation of incident investigation report with impact analysis.
7.3.2 Concerned department shall forward the break down maintenance intimation slip to engineering department.
7.4 Part-4 (For Engineering)
7.4.1 Engineering department shall acknowledge the breakdown intimation details and impact evaluation
filled by concerned department and QA.
7.4.2 Based on the trend of breakdown/maintenance history and condition evaluation of the equipment
/instrument, renewal/replacement decision shall be triggered by Engineering department in
consultation with concerned department and QA.
7.4.3 Engineering department shall evaluate the need of filing planned modification in consultation with
QA and QA shall allot planned modification number (if required) and include in break down maintenance intimation slip.
7.4.4 Engineering department shall evaluate the reason for break down and rectify the problem.
7.4.5 After maintenance, if required machine trials shall be given to the concerned department while handing it over.
7.4.6 Engineering department shall evaluate the need for the passivation and sanitization of the
rectified equipment / instrument and perform the same.
7.4.7 Engineering department shall evaluate the need for recalibration or requalification in consultation
with QA and document the same in breakdown maintenance intimation slip. QA shall inform to concerned
department and qualification team for requalification or recalibration of that equipment / instrument.
7.4.8 Equipment /instrument history card shall be updated by the engineering department and necessary
parts checked while preventive maintenance and shall be updated in the preventive maintenance checklist.
7.4.9 In case of repetitive breakdowns, the preventive maintenance frequency /schedule may be revised.
Note: All the change (modifications/ part replacements) shall be recorded in equipment
/instrument history card.
7.4.10 Engineering department shall fill the following details in the breakdown maintenance intimation
slip and shall be forwarded to concerned department along with necessary attachments like,
planned modification form, copy of updated equipment / instrument history card, passivation record,
sanitization record, machine trial report, etc., if required.
• Reason for breakdown.
• Planned modification required / not required. If required PMF (Planned modification form) no.
• Corrective action taken.
• Passivation required / not required. If required, report no.
• Sanitization required / not required. If required, report no.
• Recalibration /calibration required / not required.
• Requalification / qualification required / not required.
• SIP qualification required / not required.
• History card updated by / date.
• Maintenance report (MR) checked and forwarded to concerned department by date and time.
• Maintenance report (MR) received by concerned department, date and time.
7.5 Part-5 (For Concerned department)
7.5.1 After maintenance, the concerned department shall verify the recalibration/calibration,
SIP qualification, requalification/qualification, Passivation, sanitization status in consultation
with QA and shall include reference document number for the same.
7.5.2 The concerned department shall include closing remarks if any and shall forward the breakdown
maintenance intimation slip to QA for evaluation along with necessary attachments like, copy
of sequential log, incident investigation report etc.
7.6 Part-6 (For Quality Assurance)
7.6.1 QA shall ensure that all actions suggested in the different parts of the breakdown maintenance
intimation slip are completed and wherever not completed, shall issue CAPA and monitor the same.
7.6.2 QA shall include but not limited to following status.
• Incident investigation status.
• Planned modification status.
• Recalibration /calibration, Requalification/qualification status.
• Impact evaluation status.
• Remarks on batch(s) disposition under impact of the breakdown.
• CAPA No.
8.0 REVISION HISTORY
Version No. | 00 | Effective Date | |
Details of revision: New SOP Prepared |
Annexure-I
BREAKDOWN MAINTENANCE INTIMATION SLIP
Serial No.: | ||
Part- 1 (For concerned department)
To : Engineering |
From (Department) : Date : | |
Equipment /instrument name : | Code : | Location : |
Nature of problem : | ||
Product under impact : | ||
Batch(s) under impact : | ||
Intimated to QA by : Date : | Remarks of department head : Sign/ Date: | |
Part- 2 (For quality assurance)
Deviation/ Incident no.: Remarks for impact analysis / any other : Evaluated by : Date: |
||
Part- 3 (For concerned department)
Given for maintenance by : Date : Time : Received by (engineering) : Date: Time : |
||
Part- 5 (For concerned department)
Passivation report No.(If required) : Sanitization report No.(If required) : Recalibration / calibration record no. (if required): Requalification / qualification record no. (if required) : SIP qualification record no. (if required): Closing remark by department head: Sign : Date : |
||
Part- 6 (For quality assurance) Incident investigation status : Planned modification status : Recalibration / calibration status : Requalification / qualification status: Impact evaluation status :
Batch disposition status : CAPA no. Note: For more details provide attachments. |
Annexure-II
LOG FOR ISSUANCE OF BREAKDOWN MAINTENANCE SERIAL NUMBER
BLOCK:-
Date | Breakdown Maintenance Serial No. | Department | Equipment/ Instrument Name | Equipment/ Instrument Code | Location | Nature of Problem/ Breakdown | Serial Number Allocated by QA (Sign/Date) | Reference Deviation/ incident No.
(if any) |
Reference CAPA No. (if any) | Closure Status/ Remarks |
sop for Execution of Preventive Maintenance
Preparation of Sodium Hydroxide Solution
sop for water cooled chiller operation
cleaning and preventive maintenance of LAF and RLAF
sop for replacement of water system filters
cleaning and preventive maintenance of insectocutor
sop for operation of preventive maintenance
sop for material receiving and consumption record
sop for Preventive maintenance of bottle washing machine
sop for Replacement of Battery of Electronic Devices
sop for Preparation of R.O. Antiscalant Solution
Preventive Maintenance of Rapid Cooling Steam Sterilizer
Preventive Maintenance of Rapid cooling steam Generator
sop for Preventive Maintenance of Dust Collector
sop for Replacement of HVAC filters
SOP for Battery Backup in Mobile Laminar Air Flow Trolley
sop for Replacement of Tube lights
sop for Replacement of UV light of purified water plant
sop for Cleaning of soft water storage tank and RO feed tank
sop for Preparation of Sodium hydroxide Solution
sop for Operation and regeneration of softener plant
Procedure Of Issuance Of material from Engineering Store
sop for Preventive Maintenance of Filter Press
sop for Preventive Maintenance of Sugar Transfer System
sop for Preventive Maintenance of Shrink Sleeve Machine
sop for Preventive Maintenance of ROPP Cap Elevator
sop for Preventive Maintenance of Liquid Transfer Pumps
sop for Preventive Maintenance of Liquid Tanks
Preventive Maintenance of Strip De-Foiling Machine
sop for Preventive Maintenance of Colloidal Mill
sop for Preventive Maintenance of Packing Collator Belt
sop for Checking light intensity
sop for Operation of Fire- Extinguisher
sop for Passivation of WFI Distribution Loop
sop for Analysis of Effluent Treatment Plant Water
sop for Methodology to Dispose ETP Sludge
sop for Action Plan In Case Of Electrical Power Failure
sop for Colour Coding of Piping and Accessories of Utilities
sop for Disposal of Engineering Waste
Filter Cleaning of HVAC System RLAF & LAF
Procedure for Calibration of Magnehelic Gauge
Procedure for Calibration of Vacuum Gauge
Procedure for Calibration of Pressure Gauge
sop for Procedure for Calibration of Temperature Controller
sop for Preventive Maintenance of Infrared Dryer Umbrella Type
sop for Preventive Maintenance of Battery stacker
sop for Preventive Maintenance of Lift
sop for Preventive Maintenance of Vacuum Cleaner
sop for Preventive Maintenance of laminar air flow unit
sop for Preventive Maintenance of Lozenges Manufacturing Line
sop for Preventive Maintenance of Garment Washing Machine
sop for Preventive Maintenance of Multi Column Distillation Plant
sop for Preventive Maintenance of Steam Sterilizer Autoclave
sop for Preventive Maintenance of Pure steam Generator
sop for Preventive maintenance of Depyrogenating Tunnel
sop for Preventive Maintenance of vial sealing machine
sop for preventive maintenance of Powder Filling and Rubber Stoppering machine
sop for Preventive Maintenance of Vial Washing Machine
sop for Preventive Maintenance of Inspection Table
sop for Preventive Maintenance of Hi-Cart
sop for Preventive Maintenance of Turn table
sop for Preventive Maintenance of sticker labeling machine
sop for Preventive Maintenance of Liquid Filling and Sealing Machine
sop for Preventive Maintenance of Linear Bottle Washing Machine
sop for Preventive Maintenance of De-Foiling Machine
sop for Preventive Maintenance of Strip Packing Machine
sop for Preventive Maintenance of Blister Packing Machine
sop for Preventive Maintenance of Capsule Polishing and Sorting Machine
sop for Preventive Maintenance of Capsule Filling Machine
<script async src=”https://pagead2.googlesyndication.com/pagead/js/adsbygoogle.js?client=ca-pub-3537406586802816″
crossorigin=”anonymous”></script>
<ins class=”adsbygoogle”
style=”display:block; text-align:center;”
data-ad-layout=”in-article”
data-ad-format=”fluid”
data-ad-client=”ca-pub-3537406586802816″
data-ad-slot=”6309611142″></ins>
<script>
(adsbygoogle = window.adsbygoogle || []).push({});
</script>
sop for Preventive maintenance of Auto Coater
sop for Preventive Maintenance of Compression Machine
sop for preventive maintenance of packing conveyor belt
sop for Preventive Maintenance of Sifter Cum Multi mill
sop for Preventive Maintenance of Rapid Mixer Granulator
sop for Preventive Maintenance Of Fluid Bed Dryer
sop for Preventive Maintenance of Octagonal Blender
sop for Preventive Maintenance of Lifting and Positioning Device
sop for Preventive Maintenance of Paste Preparation vessel
sop for preventive maintenance of Vibro-Sifter
sop for preventive maintenance of air curtain
sop for preventive maintenance of air handling units
Preventive Maintenance of Diesel Generator
sop for Preventive Maintenance of cooling towers
sop for Preventive Maintenance of Boiler
sop for Preventive Maintenance of Air Compressor
sop for Preventive Maintenance of Chilling Plant
sop for Preventive Maintenance of Transformers
sop for Preventive maintenance of Purified Water System
sop for Break Down maintenance of Machine and Work Requisition
sop for Operation of Dust Extraction System
sop for Operation Of Effluent Treatment Plant
sop for Operation Of Diesel Generator
sop for Operation of Multi Column Distillation Plant
sop for Operation of Pure Steam Generator
sop for Operation of Air Handling Unit
sop for Operation of Cooling Tower
sop for Operation of Air Compressor
sop for Operation of Water Chilling Plant
sop for Cleaning of Pure Steam Generator
Cleaning of Over Head Water Tanks HDPE
sop for Cleaning of Water tanks
sop for Sanitization of multi column plant
sop for Sanitization of Ultrafiltration System
Sop for Chemical Sanitization of Reverse Osmosis
Sop for Sanitization of Hot Sanitization & Electro Deionization unit
sop for Sanitization of Purified Water Loop
sop for preparation of sodium meta bisulphate solution
sop for Testing of Hardness of Soft Water
sop for Operation & back wash of multi grade filter
sop for testing of chlorine contents in water